Tier C — closure report
Summary
- Tier C launch governance scope is complete: C0-01..C0-04 issues were created,
assigned, and linked in the Tier C dashboard.
- Kick-off was held and documented with decisions, owners, and due dates in
docs/prompts/history/2026-04-06/15-tier-c-launch/kickoff-notes.md.
- Tier C operational tracking assets are now maintainer-ready:
TIER_C_PROGRESS.md, TIER_C_HANDOVER.md, and risk log
docs/risks/tier-c-risk-log.md.
Out of scope for this closure:
- C1/C2/C3 implementation backlog remains open as post-Tier-C follow-up work.
Monitoring and verification evidence
- Tier B baseline verification (no regressions):
TIER_B_POSTLAUNCH_VERIFICATION.md
- Tier C C0 issue links:
- C0-01: https://github.com/your-org/your-repo/issues/123
- C0-02: https://github.com/your-org/your-repo/issues/124
- C0-03: https://github.com/your-org/your-repo/issues/125
- C0-04: https://github.com/your-org/your-repo/issues/126
- Tier C kickoff notes:
docs/prompts/history/2026-04-06/15-tier-c-launch/kickoff-notes.md
Operational handover
- Start here:
docs/e2e/TIER_C_HANDOVER.md
- Daily/weekly tracking:
docs/e2e/TIER_C_PROGRESS.md
- Risk register:
docs/risks/tier-c-risk-log.md
- Audit trail:
docs/prompts/history/2026-04-06/15-tier-c-launch/
docs/prompts/history/2026-04-06/16-tier-c-completion/
Follow-ups
- Execute C1/C2/C3 backlog from
TIER_C_IMPLEMENTATION_TASKS.md.
- Maintain weekly Tier C dashboard updates each Monday.
- Keep Tier A + Tier B PR CI green while Tier C follow-ups are delivered.